BWXTSep 2026Seeded
Project Pele program page
Pele core barrel cartridge installation complete Sept 2026; not yet shipped/fueled.
Small reactorsActionNeutral tone
bwxt.comKey developments first.
Reading
Pele core barrel cartridge installation complete Sept 2026; not yet shipped/fueled.
Pele reactor and power station to ship to INL in 2027 for fueling and testing.
Full Pele core of TRISO fuel at INL; formal testing as early as 2027.
BWXT starts Pele core fabrication.
SCO picks BWXT (~$300M) to build the Pele prototype.